Sprinklers changed for new offices in a tenant suite
Example project
- Building
- Tenant suite of about 2,500 sq ft on an open floor of a Battle Ground commercial building with sprinklers
- Original request
- New offices and a break room in what was one open room, with the sprinklers changed to match
- Work
- Branch lines changed and about 16 heads moved or added, with drawings and calculations for the new rooms
- Kept
- The building’s riser, main pipe and water supply
- Timeline
- Drawings and the city fire permit first, then four days of work before the ceiling grid closes
- Cost
- $8,200
In this example, a tenant in a Battle Ground commercial building is splitting an open suite of about 2,500 sq ft into offices and a break room. The floor is still an open shell with an exposed concrete ceiling. The building already has sprinklers, but the heads were laid out for one big room, and new walls would leave some spaces without coverage.