Example Fire Suppression Projects in Vancouver, Washington

Each example follows one commercial job from the first plans to the final test: the building, what the owner or tenant needed, what the work involves, how long it takes and roughly what it costs.

Hood suppression for a new café kitchen

Example project

New stainless canopy hood hanging over an empty kitchen floor, with two steel tables, utility stubs, work lights and cords
Building
Former shop space in a Vancouver retail center, being built out as a café with a full kitchen
Original request
A suppression system for the new hood, ready for the fire inspection before opening
Cook line
Two ranges, a griddle, two fryers and a charbroiler under one long hood, about 12 ft
System
Wet-chemical system with two tanks, nozzles over each appliance and in the hood and duct, a pull station and a gas shutoff valve
City fire permit
$585 for one new hood system in 2026 ($350 plan review and $235 inspection), included
Timeline
Several weeks of plan review, then two days of work once the appliances are in place
Cost
$10,900

Scope of work

A layout drawn from the appliance list and hood drawings, the permit submitted, then the tank, piping and nozzles over each appliance and in the hood and duct, detection, a pull station by the exit path, a gas shutoff valve and its link to the system, a full function test and the city acceptance test. The hood, the exhaust fan and the gas and electrical work are part of the build-out.

Project overview

In this example, a café is going into an empty shop space in a Vancouver retail center. The new hood, about 12 ft long, already hangs from the ceiling over bare floor and utility stubs, and two ranges, a griddle, two fryers and a charbroiler will sit under it.

The system is drawn from the final appliance list, not from the hood size alone, because each nozzle is aimed at one cooking surface. The plans go to the city early, and the tank and piping go in once the appliances are set in their final spots.

The goal

The goal is a café kitchen that passes its fire inspection on schedule, with a system laid out for the appliances it actually has.

Process

  1. Before work Appliance list and hood drawings collected, the layout drawn and the permit submitted.
  2. Plan review The city reviews the drawings while the build-out carries on.
  3. Day one Tank, piping, nozzles and detection fitted once the appliances are in place.
  4. Day two Pull station and gas shutoff connected, then a full function test.
  5. Before opening City acceptance test, then the system is tagged as ready.

Planning right

  • Send the final appliance list, not a wish list. A change after the design means new drawings.
  • Put the pull station on the way out of the kitchen, where staff pass it when they leave.
  • Keep the appliances where the nozzles point. Moving one later means the system has to be checked again.
  • Book the fire inspection early. It is one of the last steps before opening.

Get a free quoteMore about kitchen hood suppression

A new hood system after the cook line changes

Example project

Long stainless hood over a commercial cook line with ranges, a griddle and a fryer in a bright kitchen
Building
Restaurant in Vancouver with one long hood, about 12 ft
Original request
New appliances in a new order under the same hood, and a system that protects them
Cook line
Ranges, a griddle and a two-basket fryer, with the fryer moved to the other end of the line
Work
The old system taken out and a new wet-chemical system with two tanks fitted for the new line
City fire permit
Included; a new hood system carries $585 in city fees in 2026
Timeline
Plan review first, then one night and one morning of work so the kitchen closes for one service only
Cost
$9,800

Scope of work

The old system disconnected and taken out, a new two-tank system laid out for the new appliance positions, nozzles over each appliance and in the hood and duct, new detection, the existing pull station and gas shutoff tested and reconnected, a full function test and the city acceptance test. The appliances and any gas changes are separate.

Project overview

In this example, a Vancouver restaurant is replacing its ranges, griddle and fryer, and the fryer moves to the other end of the line. The old system was laid out for the old line, so its nozzles would no longer point at the right cooking surfaces.

Rather than rework an old system around a new line, the owners choose a new two-tank system laid out for the new appliances. The work is planned around service hours, so the kitchen loses only one service.

The goal

The goal is a cook line where every appliance sits under a nozzle aimed at it, back in service after one closed shift.

Process

  1. Before work Old and new appliance layouts compared, the new system drawn and the permit submitted.
  2. Plan review The city reviews the new layout while the appliances are ordered.
  3. After the last service Old system out, new appliances set and the new tanks, piping and nozzles fitted overnight.
  4. Next morning Detection, pull station and gas shutoff connected and tested.
  5. Before reopening City acceptance test, then the kitchen reopens.

Planning right

  • Any change to the cook line is a reason to have the system checked, even if the hood stays.
  • Give the designer the old system papers too. They show what can be reused.
  • Plan the work for the quietest service of the week.
  • Keep the new layout drawing in the kitchen office. The next appliance change starts from it.

Get a free quoteMore about kitchen hood suppression

Sprinklers changed for new offices in a tenant suite

Example project

Empty concrete floor with an exposed ceiling, new red sprinkler pipes and pendant heads, ductwork and windows
Building
Tenant suite of about 2,500 sq ft on an open floor of a Battle Ground commercial building with sprinklers
Original request
New offices and a break room in what was one open room, with the sprinklers changed to match
Work
Branch lines changed and about 16 heads moved or added, with drawings and calculations for the new rooms
Kept
The building’s riser, main pipe and water supply
Timeline
Drawings and the city fire permit first, then four days of work before the ceiling grid closes
Cost
$8,200

Scope of work

The new wall and ceiling plans checked against the existing heads, drawings and calculations for the changed rooms, the permit through Battle Ground, branch lines changed, about 16 heads moved or added, a pressure test, the city inspection while the ceiling is open, and the ceiling heads set to the finished grid. Ceilings and walls belong to the remodel.

Project overview

In this example, a tenant in a Battle Ground commercial building is splitting an open suite of about 2,500 sq ft into offices and a break room. The floor is still an open shell with an exposed concrete ceiling. The building already has sprinklers, but the heads were laid out for one big room, and new walls would leave some spaces without coverage.

The designer works from the final wall and ceiling plans, so each new room gets the heads it needs. The pipe work is done while the ceiling is open, and the inspection comes before the ceiling grid closes.

The goal

The goal is new offices with full sprinkler coverage, inspected before the ceiling closes and on the building’s existing system.

Process

  1. Before work Wall and ceiling plans collected, the changes drawn and calculated, and the city fire permit applied for.
  2. Days one to three Branch lines changed and heads moved or added in the open ceiling.
  3. Day four Pressure test, then the city inspection.
  4. After the ceiling Heads set to the finished ceiling and the system checked.

Planning right

  • Send the ceiling plan with the wall plan. Lights and vents decide where heads can go.
  • Ask the building owner for the sprinkler drawings early. They save design time.
  • Leave a day between the inspection and the ceiling crew.
  • A small change to the walls can still change the sprinklers. Ask before the walls go up.

Get a free quoteMore about commercial fire sprinklers

Ten sprinkler heads moved for two new offices

Example project

Block-walled riser room with a red sprinkler riser, valves, two pressure gauges and a floor drain
Building
Warehouse and office building in Camas with an existing sprinkler system
Original request
Two private offices built in an open office area, with the sprinklers changed to suit
Work
About 10 heads moved or added, the system drained at the riser and refilled
Kept
The riser, valves and main pipe
Timeline
Permit first, then one working day with the system off for part of it
Cost
$4,300

Scope of work

The new office walls checked against the existing heads, the fire permit through Camas, the fire department and alarm company told before the system is turned off, the system drained at the riser, about 10 heads moved or added with short pipe changes, the system refilled, vented and pressure tested, valves reopened and checked, and the inspection. Walls and ceilings belong to the remodel.

Project overview

In this example, the owner of a warehouse and office building in Camas is adding two private offices inside an open office area. New walls put some heads in the wrong place and leave the new rooms short, so about 10 heads need to move or be added.

The system is turned off at the riser for only part of one working day. The fire department and the alarm company are told first, the heads are changed, and the system is refilled and checked before everyone goes home.

The goal

The goal is two new offices with sprinklers where they belong, and the building back under full protection by the end of the day.

Process

  1. Before work New wall plan checked against the heads, the permit applied for and the shutdown day agreed.
  2. Morning Fire department and alarm company told, the system turned off and drained at the riser.
  3. Midday Heads moved or added, pipe changes made.
  4. Afternoon System refilled, vented and tested, valves reopened, and the alarm company told it is back.
  5. Then Inspection of the changed heads.

Planning right

  • Plan the shutdown for a quiet day. While the system is off, the building has less protection.
  • Moving a few heads still needs the right permit route. Ask before the walls are framed.
  • Ask for the valves to be checked open at the end of the day.
  • Keep the changed drawing with the building’s sprinkler records.

Get a free quoteMore about commercial fire sprinklers

Sprinklers added to an office building that had none

Example project

Empty office floor with glass-walled offices, a polished concrete floor and tall windows
Building
Single-story office building in Vancouver, about 5,000 sq ft, with no sprinklers
Original request
Sprinklers throughout before the building is leased to new tenants
Work
A new sprinkler system with about 35 heads, fed from a new riser on the existing water service
City fire fees
$932 in 2026 ($291 plan review and $291 inspection, plus $10 a head for about 35 heads), included
Not included
The backflow assembly at the riser, and any new underground fire line
Timeline
A water flow test and drawings, plan review, then about two weeks of work
Cost
$31,000

Scope of work

A water flow test, design drawings and calculations, the city review, a riser with its valves on the existing water service, pipe run above the ceiling to about 35 heads, a pressure test, the city inspection, and the ceiling tiles and finishes put back where pipe went through. The backflow assembly the water supplier requires at the riser is priced separately, and so is a new underground fire line if one were needed.

Project overview

In this example, the owner of a single-story office building in Vancouver wants sprinklers throughout before leasing it to new tenants. The building is about 5,000 sq ft and has none.

The water supply decides the rest, so a flow test comes first. Here it shows the existing service has enough flow and pressure, so a new riser goes on it, with a backflow assembly fitted there to keep sprinkler water out of the drinking water. That assembly is priced on its own. Pipe then runs above the ceiling to about 35 heads. Adding sprinklers to a finished building costs more than to a new one, because the pipe has to go in around ceilings, lights and walls that are already there.

The goal

The goal is a building fully covered by sprinklers before new tenants move in, on the water service it already has.

Process

  1. Before design Water flow test at the nearest hydrant and the building measured.
  2. Design Drawings and calculations made and sent to the city for review.
  3. Weeks one and two Riser set, pipe run above the ceiling, heads fitted room by room.
  4. Testing System held under pressure for the test, then the city inspector’s visit.
  5. Last days Ceiling tiles and finishes put back, and the drawings and records handed over.

Planning right

  • Order the flow test first. It shows whether the existing water service has enough flow and pressure.
  • Work between tenants if you can. An empty building is faster and cheaper to work in.
  • Ask whether the alarm company needs to add monitoring. It is usually a separate contract.
  • Keep the drawings and test records for leasing and for the next tenant improvement.

Get a free quoteMore about commercial fire sprinklers

Clean-agent protection for a server room

Example project

Small server room with three black server racks, gray walls and a plain gray floor
Building
Office building in Vancouver with a server room of about 450 sq ft
Original request
Fire protection for the server room that does not use water on the equipment
System
Clean-agent cylinders, piping and nozzles, smoke detection and a release panel
Room
Door seal added and gaps around pipes and cables in the walls sealed so the room holds the agent
City fire permit
$1,167 for a fixed system in 2026 ($486 plan review and $681 inspection), included
Timeline
Plan review, then three days of work and a full test
Cost
$9,400

Scope of work

A room survey and agent calculation, the city review, agent cylinders, piping and nozzles, smoke detection, a release panel with an abort switch and warning signs, a door seal and the wall gaps sealed, a room check that it holds the agent, a full function test and the city inspection. The building sprinklers stay as they are.

Project overview

In this example, a company in a Vancouver office building keeps its servers in a room of about 450 sq ft. The owners want protection that puts out a fire without water reaching the equipment.

A clean-agent system floods the room with a gas that leaves no residue, so the room has to hold it. The survey finds gaps where cables pass through the walls and a door with no seal, so those are closed before the system is tested.

The goal

The goal is a server room protected without water, sealed well enough to hold the agent, with staff who know the controls.

Process

  1. Before work Room measured, equipment listed, the agent amount worked out and the plans sent to the city.
  2. Day one Cylinders mounted and pipe run to the nozzles in the ceiling.
  3. Day two Detection, release panel, abort switch and signs fitted; the door seal added and wall gaps sealed.
  4. Day three Room check and full function test with no agent released.
  5. Then City inspection, then the system is put in service.

Planning right

  • Every new cable through the wall later is a new gap. Seal it the same day.
  • Train staff on the abort switch and what the warning signs mean.
  • Keep the door closed. A propped-open door lets the agent out.
  • The room’s sprinklers usually stay. Ask how the two systems work together.

Get a free quoteMore about clean-agent systems for equipment rooms

Clean agent for an equipment room in a new tenant space

Example project

Four red clean-agent cylinders strapped to the walls of an equipment room, with red pipes overhead and a control cabinet
Building
Light-industrial building in Washougal, with a new tenant moving into one unit
Original request
Protection for a control and equipment room of about 1,000 sq ft, built as part of the move-in
System
Four red agent cylinders in two pairs on the walls, overhead pipe to the nozzles, detectors and a release panel
Room
New walls built all the way up to the roof structure, with the door and every gap sealed
Timeline
Designed with the tenant improvement; four days of work after the walls are finished
Cost
$12,500

Scope of work

A survey of the planned room and its equipment, the agent calculation, the fire permit for the Washougal address, cylinders, piping and nozzles, detection, a release panel with an abort switch and signs, a room check that it holds the agent, a full function test and the inspection. The walls, door and sealing are part of the tenant improvement.

Project overview

In this example, a new tenant is moving into one unit of a light-industrial building in Washougal and is building a control and equipment room of about 1,000 sq ft. The room did not exist before, so the protection is planned with the walls.

Planning it early means the walls go all the way up to the roof structure and every gap is sealed as it is built, which makes the room check simple. The four cylinders stand in two pairs against the walls, with red pipe running overhead to the nozzles.

The goal

The goal is a new equipment room protected from the day the tenant opens, built to hold the agent from the start.

Process

  1. With the TI design Room size, equipment list and wall details agreed, the agent amount worked out.
  2. Permit Plans submitted for the Washougal address.
  3. After the walls Cylinders strapped to the walls, pipe and nozzles run, detection and panel fitted.
  4. Testing Room check, full function test and the inspection.

Planning right

  • Plan the room and its protection together. Sealing walls later costs more.
  • Leave wall space for the cylinders, with room to reach them.
  • List the equipment going in. It decides how the room is protected.
  • Tell the landlord early. The system belongs in the lease papers.

Get a free quoteMore about clean-agent systems for equipment rooms

A server room doubles in size and gets a new system

Example project

Metal clean-agent discharge nozzle in a dropped ceiling above a row of server racks
Building
Business-park building in Ridgefield, with a tenant that already has a protected server room
Original request
Join the server room to the room next door, about 2,000 sq ft in all, and keep it protected
Found
The existing system holds too little agent for the larger room
Work
Old system taken out and a new one sized for the joined room, with new nozzles in the dropped ceiling
Timeline
Design and the fire permit first, then about a week of work with the servers running
Cost
$17,500

Scope of work

The existing system papers reviewed, the joined room surveyed and the agent worked out, the fire permit for the Ridgefield address, the old system taken out, new cylinders, piping and nozzles, detection and a release panel, a room check that the larger room holds the agent, a full function test and the inspection. Opening the wall between the rooms is part of the remodel.

Project overview

In this example, a tenant in a Ridgefield business park is joining its protected server room to the room next door, for about 2,000 sq ft in all. The existing clean-agent system was sized for the smaller room.

More room needs more agent, and the old cylinders and pipe cannot supply it, so a new system replaces the old one. The servers keep running, so the work is staged: the old system stays in service until the new one is ready to switch on.

The goal

The goal is a larger server room that stays protected the whole time, with a system sized for the room it is now.

Process

  1. Before work Old system papers reviewed, the joined room surveyed and the permit applied for.
  2. Days one to three New cylinders mounted, pipe and nozzles run in the dropped ceiling with the old system still live.
  3. Day four Detection and release panel fitted, then the switch-over to the new system.
  4. Day five Old system taken out, room check and full function test.
  5. Then Inspection, and the new system papers handed over.

Planning right

  • Any change to a protected room is a reason to have the system checked, even a small one.
  • Keep the old system papers. They show what was there and why.
  • Plan the switch-over for a quiet time, with staff told when the panel changes.
  • The joined room has to hold the agent too. The new wall openings are sealed before the test.

Get a free quoteMore about clean-agent systems for equipment rooms

Request a free fire suppression quote

Tell us the address, what the space is used for, which system you need and whether drawings or old system papers exist. We'll get back to you soon to arrange a visit or with any questions we have. Estimates are free and there's no obligation.

Call (360) 566-6964